11 Apr 2019 POSTED BY: ADMIN
Red Rock have been geotechnical consultants for the £14m redevelopment of the historic Victorian fort of Fort Bovisand lying on the eastern approaches to Plymouth Sound.
11 Apr 2019 POSTED BY: ADMIN
Red Rock undertook ground investigations and inspections of a section of cliff to provide a design for the slope stabilisation of a coastal cliff section.
12 Mar 2019 POSTED BY: ADMIN
A new student village at East Park for the University of Exeter comprising 11 tower blocks of student accommodation and commercial premises.
30 Jun 2017 POSTED BY: ADMIN
Works on this historic site involved the demolition and refurbishment of existing structures and extensive soil remediation.
11 Apr 2019 POSTED BY: ADMIN
Ground investigation, slope assessment, and stabilisation design for a new private property.
30 Jun 2017 POSTED BY: ADMIN
A former clay dryer site where works involved decommissioning, remediation, and restoration of the site.
30 Jun 2017 POSTED BY: ADMIN
Red Rock have considerable experience in ground investigations on quaysides and over water.
30 Jun 2017 POSTED BY: ADMIN
Works on this derelict community centre involved extensive asbestos remediation and validation testing.
12 Apr 2019 POSTED BY: ADMIN
Red Rock undertook a ground investigation for foundation and slope stability design for the re-development of a residential property at St Agnes.
30 Jun 2017 POSTED BY: ADMIN
The site has been a glove dyeing and manufacturing factory since the mid-1800s and investigations were required ahead of future re-development.
20 Apr 2017 POSTED BY: ADMIN
A former undeveloped corner of a residential area which had suffered from unregulated tipping leading to extensive contamination by asbestos insulation materials and fibres.
30 Jun 2017 POSTED BY: ADMIN
This high profile re-development involved detailed investigations, culminating in extensive soil and remediation works.
11 Apr 2019 POSTED BY: ADMIN
Red Rock undertook the stabilisation design of a section of failing slope affecting a public road.